Timeline for billion-dollar North Shore wastewater treatment plant uncertain after project 'abandoned'
Construction on the new North Shore sewage treatment plant, already years behind its initial timeline for completion, has slowed so significantly that Metro Vancouver now considers the project “abandoned” by the contractor.
In a statement, Metro Vancouver told CTV News the project contractor, Acciona Wastewater Solutions LP, significantly reduced staff last Wednesday without notice.
Metro Vancouver, which represents nearly two dozens municipalities and oversees and operates regional wastewater treatment facilities, said the contractor had just 50 people remaining on staff following layoffs, down from 300 earlier in the year.
“We’re committed to completing the project, and are actively assessing our options for how to proceed and ensure it is delivered in the best interest of the region,” said Jerry Dobrovolny, Metro Vancouver’s commissioner and chief administrative officer.
On Monday it appeared some work was continuing at the site, with cranes and diggers operating and traffic on West 1st Street, which borders the site, slowed to alternating single lane.
CTV News has reached out to Acciona Canada via email and phone for comment and will update this article when it receives a response.
With an initial completion date set for December 2020, the North Shore Wastewater Treatment Plant is already years behind schedule.
Its costs have ballooned from $700 million, some $400 million of which is being funded by the federal and provincial governments, to over $1 billion.
According to Metro Vancouver, the project contract was revised in 2019 to give Acciona an extra two-and-a-half years because of challenges that included difficult ground conditions, space requirements, and geotechnical complications.
The new setback now calls the revised 2023 completion date into question, with Metro Vancouver noting Acciona has “fallen behind meeting key milestones.”
“Metro Vancouver expects the contractor to continue to work in good faith to meet the terms of the contract including all health and safety requirements,” Dobrovolny said.
Acciona, based in Spain, describes itself as “a global provider of sustainable solutions for infrastructure and renewable energy projects” that “has successfully delivered large infrastructure projects across Canada since 2001.”
The company, as part of two different consortiums, is also heading up design and construction on Vancouver’s Broadway subway extension, as well as the Pattullo Bridge replacement.
Minister of Transportation and Infrastructure Rob Fleming told CTV News he was “concerned for Metro Vancouver” with respect to the water treatment plant, but not concerned when it came to the two transportation projects.
“They’re on budget and on time,” Fleming said. “Major things are happening and we’ve experienced no problems like (those in North Vancouver)."
The wastewater treatment plant, which would serve a quarter of a million North Shore residents, would replace the existing plant under the Lions Gate Bridge, and return the land on which that plant operates to the Squamish Nation.
A spokesperson for the District of West Vancouver deferred inquiries back to Metro Vancouver.
North Vancouver District Mayor Mike Little provided a statement that didn’t address the potential setback, and instead read: “Our role is limited to issuing permits as required.”
CTV News has also reached out to the Squamish Nation and the City of North Vancouver.
CTVNews.ca Top Stories
DEVELOPING Live updates as Stormy Daniels testifies at Trump hush money trial
Adult film star Stormy Daniels will take the stand a second time Thursday as former U.S. president Donald Trump’s hush money case continues in Manhattan. Follow live updates here.
BREAKING Toronto Maple Leafs fire head coach Sheldon Keefe
The Toronto Maple Leafs have fired head coach Sheldon Keefe. The team made the announcement Thursday after the Original Six franchise lost to the Boston Bruins in seven games in the first round of the Stanley Cup playoffs.
Bank of Canada says financial system is stable, but risks remain
The Bank of Canada says the Canadian financial system is stable, but risks remain due to debt servicing costs among households and businesses and stretched valuations of financial assets.
Why these immigrants to Canada say they're thinking about leaving, or have already moved on
For some immigrants, their dreams of permanently settling in Canada have taken an unexpected twist.
Here are the ultraprocessed foods you most need to avoid, according to a 30-year study
Studies have shown that ultraprocessed foods can have a detrimental impact on health. But 30 years of research show they don’t all have the same impact.
Court to hear about search for remains as Winnipeg murder trial enters second day
A courtroom in Winnipeg is expected to hear testimony today about the search for the remains of the four victims of Jeremy Skibicki.
Capital gains tax change 'shortsighted' and 'sows division' business groups tell Freeland
Forging ahead with increasing Canada's capital gains inclusion rate 'sows division,' and is a 'shortsighted' way to improve the deficit, business groups are warning Finance Minister Chrystia Freeland.
Ontario man frustrated after $3,500 paving job leaves driveway in shambles
An Ontario man considering having his driveway paved received a quote from a company for $7,000, but then, another paver in the neighbourhood knocked on his door and offered half that rate.
'We can and we must do better': First ever Air Accessibility Summit hits Ottawa
Federal ministers, airline executives and members of the disability community are gathering in Ottawa today for the first ever Air Accessibility Summit.